Life afterwards
Dams and reservoirs
Cleveland and Seymour Falls dams hold two of Metro Vancouver’s drinking water reservoirs in North Shore mountain valleys. Both carry the province’s top consequence rating. Engineers reviewed both dams in 2024. Neither published conclusion mentions an earthquake.
Last reviewed
At a glance
Engineers reviewed Cleveland and Seymour Falls dams in 2024, as required every seven years for dams in the top consequence class. Neither review identified an unsafe condition, and neither published conclusion mentions earthquakes.
Source: GVWD Dam Safety Program Annual Update for 2025 ↗ · Metro Vancouver / GVWD, Water Services (Director, Dam Safety) · 18 Jun 2026
Two water-supply dams carry the top consequence rating
Metro Vancouver has fourteen regulated dams. Two of them, Cleveland and Seymour Falls, hold back reservoirs in the region’s drinking water supply, and both are classified “Extreme” failure consequence, the top of the province’s five-tier scale.
That scale measures consequence, not hazard. It describes what is below a dam, and it is assigned before anyone assesses how the dam itself would perform. The Regulation sorts dams by potential loss of life, and Extreme is its top band, for “more than 100”, where the population at risk is permanent: people “ordinarily or regularly located in the dam-breach inundation zone, whether to live, work or recreate”.

What an earthquake is expected to do to the region’s dams, and every dam the province classes Extreme or Very High failure consequence in the Lower Mainland, are on dams. This page is the drinking water side of the same two structures.
Both dams sit at risk level “3 – Stable” in the provincial register, which is how the regulator records that it has not flagged a deficiency at either one. That is also the ceiling: no Extreme dam in British Columbia is rated better than 3, and 20 of the province’s 56 are rated worse.
The 2024 reviews found no unsafe condition
A dam in that class must be reviewed every seven years by an engineering professional qualified in dam safety analysis, to determine whether it is safe, with the report submitted to a provincial dam safety officer for acceptance. Metro Vancouver publishes the status of each of its dams once a year, in a report to its Water Committee.
Cleveland Dam’s review ran from 2023 to 2024 and “identified no unsafe or unacceptable conditions related to design, construction, or operation”; the consultant’s report went to the province that December. Seymour Falls Dam’s ran from 2021 to 2024, with the report submitted in June 2024:
“The review concluded that the dam is reasonably safe, operated safely, maintained in a safe condition, and that surveillance is adequate to detect any developing safety problems.”
A review ends in one of three verdicts, signed by an engineer and peer-reviewed by a second: reasonably safe, reasonably safe with deficiencies, or not safe with deficiencies requiring urgent action. “Reasonably safe” is the first of those, and the province treats it as equivalent to the Regulation’s own word, “safe”.
The published conclusions do not mention earthquakes
Metro Vancouver has published one of these updates every year since 2021, each naming every dam and its review status. None of them says anything about how either dam would behave in an earthquake. The reports themselves are not published, and the consultants who wrote them are not named.
The capital program is published. It leaves the seismic question open.
| Project | Stage at 31 May 2026 | Timeline | Estimate |
|---|---|---|---|
| Cleveland Dam Seismic Stability Evaluation | Design | 2024–2027 | $1.2 million |
| Seymour Falls Dam Seismic Stability Assessment | Design | 2025–2032 | $14.15 million |
| Cleveland Dam MCE Seismic Upgrades | Not started | 2028–2034 | $25 million |
MCE stands for Maximum Credible Earthquake, one half of the criterion the province’s design guideline sets for a dam in this class; what that criterion is, and the three things that have to travel with it, are on dams. Metro Vancouver is still paying for the evaluations and has not begun the upgrade.

Both dams are inspected weekly
Between reviews, Metro Vancouver reports site surveillance at least weekly at both dams and formal inspections twice a year, and geotechnical and lake level instrumentation “is reviewed by staff daily (Monday – Friday) through an automated data acquisition system”. Each of those intervals is what the Regulation’s schedule requires of a dam in this class. Cleveland’s two low-level outlet valves, original equipment from the 1950s found badly deteriorated in a 2016 condition assessment, were replaced in 2021.
A provincial dam safety officer audits a dam in this class about every five years. The last audits of Cleveland and Seymour Falls were completed in 2020, and as of June 2026 follow-up audits “are being planned”. In September 2021, on an audit covering 2019 and 2020, the Auditor General of British Columbia found that the ministry “has not effectively overseen the safety of dams in B.C.” All nine recommendations were accepted; two were complete as at 31 March 2025, when the province’s dam safety program reported 10 staff against an assessed need of 25 and said it was “only able to target the very highest risk dams”.
Flood maps exist but are not public
The owner of a dam in this class must prepare an emergency plan and submit it to the province for acceptance, and the province’s template requires an evacuation area map to be inserted in it. Both dams’ plans were updated in March 2026. So the area a failure would flood has been mapped. It had to be: the consequence classification is worked out from who is in it.
The province gets the plan in full. A downstream local emergency authority gets a defined part of it, which the province’s controlled-copy register lists as sections 1, 2 and 4.1 and part of appendix A. The public gets none of it. Nobody has explained why, because the regime never raises the question: it carries no duty to publish an emergency plan or an inundation study, and no confidentiality rule covering one either. BC Hydro publishes dam failure evacuation brochures for Campbell River and the Strathcona Regional District, both on Vancouver Island, and nothing comparable for any of its Lower Mainland dams.
Earthquakes are in those plans even though they are absent from the review summaries. The template lists three of them among the events that escalate a dam emergency: an earthquake felt or reported within 50 kilometres of the dam, one causing visible damage to the dam, and one causing an uncontrolled release of water.
What you can do
Flood maps show who lives below these dams, but the maps are not public.
- Find out whether you live, work or send a child to school below one of them. The area a failure would flood has been mapped, because the dam’s classification is worked out from it, and the map sits in the dam emergency plan.
- Ask your municipality for the part of the plan it holds. A downstream local emergency authority receives a defined part of the plan, and nothing in the regime stops it from telling you what is in it.
- Ask Metro Vancouver for the rest. There is no duty to publish an emergency plan and no rule against releasing one, so a freedom-of-information request is the route.
- Know what the sirens below Cleveland Dam will mean, and what they will not. Metro Vancouver is building the Capilano River Evacuation System, targeted for 2027, for an unscheduled release from the dam. It does not sound for heavy rain or spring melt, and it is not a dam breach or earthquake warning.
Two engineers reviewed these dams in 2024 and neither found an unsafe condition. What has not been published is where the water would go, and the part of that concerning your own address is something you can ask for.
The full preparedness planSources on this page
Numbered in the order they are cited. Each entry links back to where it is used.
- [1]ReportCleveland Dam fact sheetMetro VancouverOpen the document ↗
- [2]ReportSeymour Falls Dam fact sheetMetro VancouverOpen the document ↗
- [3]ReportGVWD Dam Safety Program Annual Update for 2025Metro Vancouver / GVWD, Water Services (Director, Dam Safety) · 2026Open the document ↗
- [4]ReportCapital Expenditures as of May 31, 2026Metro Vancouver / GVWD · 2026Open the document ↗
- [5]DatasetBC DamsMinistry of Water, Land and Resource StewardshipOpen the document ↗
- [6]ReportDam Safety Regulation, B.C. Reg. 40/2016, under the Water Sustainability ActKing's Printer, British Columbia · 2016Open the document ↗
- [7]ReportInformation SheetB.C. Dam Safety Program · 2023Open the document ↗
- [8]ReportGVWD Dam Safety Program Annual Update for 2020Metro Vancouver / GVWD · 2021Open the document ↗
- [9]ReportGuidelines for Dam Design and ConstructionBC Ministry of Water, Land and Resource Stewardship, Dam Safety Section · 2026Open the document ↗
- [10]ReportWater Services Asset Maintenance and Replacement HighlightsMetro Vancouver / GVWD · 2021Open the document ↗
- [11]ReportOversight of Dam Safety in British Columbia — An independent audit reportOffice of the Auditor General of British Columbia · 2021Open the document ↗
- [12]ReportFollow-up on Recommendations (2019–2023)Office of the Auditor General of British Columbia · 2025Open the document ↗
- [13]ReportInstructions, Guide & Templates for Preparing a Dam Emergency Plan (DEP) in British ColumbiaB.C. Dam Safety Program · 2024Open the document ↗
- [14]ReportEstimating Dam Break Downstream InundationB.C. Dam Safety Program · 2016Open the document ↗
- [15]ReportDam Safety FAQBC HydroOpen the document ↗
- [16]ReportCleveland Dam Safety Enhancements Program page, with the Water Committee report of 13 May 2021 and its slide deckMetro Vancouver · 2021Open the document ↗